Stybarrow DTM Tracksaw Cutting
Stybarrow Fields, AustraliaC1-10T Tracksaw850m
850m
Water Depth
25mm Steel Plate
Material
10x faster
Speed vs Grinder
Project Overview
Decom Engineering was engaged by McDermott to deliver a critical subsea cutting operation as part of Woodside's Stybarrow decommissioning. The C1-10T Tracksaw was deployed via ROV basket and operated by ROV to perform precise linear cuts on 25mm thick steel plate at 850m depth. The Tracksaw achieved cutting speeds approximately 10x faster than a traditional super grinder.
Key Highlights
- 10x faster than traditional super grinder methods
- Clamped design eliminated kickback and protected blade tips
- Easily handled by a single ROV in deepwater conditions