Case Study:
Stybarrow
Flowline


Location – Stybarrow Fields, Australia

Client – MMA

Operator – Woodside


Decom Engineering was engaged by MMA to deliver a critical subsea cutting operation as part of Woodside’s decommissioning activities in the Stybarrow fields, offshore Western Australia. The project required the precise cutting of a 4” flexible flowline at a water depth of 850 meters to enable safe recovery and inspection of the infrastructure.

The C1-24 chop saw fleet (units 102 and 108) was deployed via crane and powered subsea by an ROV, with Decom-supplied hotstabs supporting the operation. The goal: clean, efficient cuts to facilitate
NORMs (Naturally Occurring Radioactive Materials) inspection and ensure the line was free of internal obstruction prior to recovery.


Solution

Decom Engineering deployed the C1-24 chop saw (units 102 and 108) to complete over 100 cuts on a 4” flexible flowline at 850 meters water depth. Powered subsea by ROV and supported with Decom-supplied hotstabs, the saw achieved an average cut time of just 3 minutes per cut.

The operation delivered clean, precision cuts—enabling immediate NORMs inspection and verification of no internal blockages without additional intervention. A rapid 10-minute cycle from cut to cut across 12-meter spacings ensured the client met critical project deadlines, while achieving the fastest clean cutting time available on the
market.

Material
4” Flexible Flowline

Deployment Method
Crane deployed, powered
via ROV with Decom-
supplied hotstabs

Water Depth
850m

Average Cut Time
3 minutes

Number of Cuts
100+

MMA Offshore Logo
woodside energy

Ask us a question

Providing solutions through innovation, reliability, and unparalleled customer service

Have questions or need assistance? We’re here to help! Get in touch with our team today to learn more about our comprehensive range of solutions, including the C1 Chopsaw Range, Pipeline Coating Removal, Inspection, Repair, and Maintenance services.

Request A Quote