Case Study: Stybarrow DTM


Location – Stybarrow Fields, Australia

Client – McDermott

Operator – Woodside


Decom Engineering was engaged by MMA to deliver a critical subsea cutting operation as part of Woodside’s decommissioning activities in the Stybarrow fields, offshore Western Australia.

The project required the precise cutting of a 4” flexible flowline at a water depth of 850 meters to enable safe recovery and inspection of the infrastructure. The C1-24 chop saw fleet (units 102 and 108) was deployed via crane and powered subsea by an ROV, with Decom-supplied hotstabs supporting the operation. The goal: clean, efficient cuts to facilitate NORMs (Naturally Occurring Radioactive Materials) inspection and ensure the line was free of internal obstruction prior to recovery.


Solution

The C1-10T Tracksaw achieved cutting speeds approximately 10 times faster than a traditional super grinder, significantly reducing subsea intervention time. Its clamped design eliminated kickback, protecting blade tips from breakage and extending blade life throughout the operation.

The saw delivered consistent, controlled cuts across the DTM structure, enabling efficient decommissioning activities while being easily handled by a single ROV. The custom-engineered solution ensured safe, reliable, and rapid cutting performance in deepwater conditions.

c1-10 chopsaw in Australia
Material
25mm Steel Plate
Deployment Method
Deployed in ROV basket, operated by ROV
Water Depth
850m
Cut Type
Precise linear cuts on 25mm thick steel plate
woodside energy
Mcdermott logo

Ask us a question

Providing solutions through innovation, reliability, and unparalleled customer service

Have questions or need assistance? We’re here to help! Get in touch with our team today to learn more about our comprehensive range of solutions, including the C1 Chopsaw Range, Pipeline Coating Removal, Inspection, Repair, and Maintenance services.

Request A Quote