CASE STUDY

C1 Chop Saw – Africa – FPSO Decommissioning

LOCATION

Mauritania, Africa

PRODUCTS

C1-24 Saw
Havfram: Petronas Chinguetti, Mauritania
TERMINATION HEAD, 10’’ PRODUCTION & 6’’ GAS INJECTION

Decom Engineering was the sole cutting contractor for this scope, for both topside and subsea operations. This involved the cutting of 84mm R4 studless mooring chains, umbilicals and termination heads. 100+ cuts were completed ahead of schedule, resulting in saved vessel time.

PROJECT OVERVIEW

Material: 508mm OD x 40mm WT, X70 steel. Duplex 152mm / 254mm, OD x 38mm WT inner, HD Polyurethane filler.

Water Depth: 900 – 1,000m

Deployment Method: ROV work pack, via hot stabs

Average Cut Time: Termination head: 30 mins; 84mm Mooring Chain: 3 mins; Umbilical: 2 minutes

Blade: 3 – 5 cuts per blade

SOLUTION PROVIDED

Full Equipment and Service Solution

Additional Services: Project management; in-house technicians; logistics management

Additional Equipment and Handling: Hot stabs; buoyancy and other equipment from trusted partners  – supplied on cross-hire

-

Termination Head, 10’’ Production & 6’’ Gas Injection

CASE STUDY

C1 Chop Saw – Africa – FPSO Decommissioning

LOCATION

Mauritania, Africa

PRODUCTS

C1-24 Saw
Havfram: Petronas Chinguetti, Mauritania
TERMINATION HEAD, 10’’ PRODUCTION & 6’’ GAS INJECTION

Decom Engineering was the sole cutting contractor for this scope, for both topside and subsea operations. This involved the cutting of 84mm R4 studless mooring chains, umbilicals and termination heads. 100+ cuts were completed ahead of schedule, resulting in saved vessel time.

PROJECT OVERVIEW

Material: 508mm OD x 40mm WT, X70 steel. Duplex 152mm / 254mm, OD x 38mm WT inner, HD Polyurethane filler.

Water Depth: 900 – 1,000m

Deployment Method: ROV work pack, via hot stabs

Average Cut Time: Termination head: 30 mins; 84mm Mooring Chain: 3 mins; Umbilical: 2 minutes

Blade: 3 – 5 cuts per blade

SOLUTION PROVIDED

Full Equipment and Service Solution

Additional Services: Project management; in-house technicians; logistics management

Additional Equipment and Handling: Hot stabs; buoyancy and other equipment from trusted partners  – supplied on cross-hire

Termination Head, 10’’ Production & 6’’ Gas Injection

CASE STUDY

C1 Chop Saw – Africa – FPSO Decommissioning

LOCATION

Mauritania, Africa

PRODUCTS

C1-24 Saw
Havfram: Petronas Chinguetti, Mauritania
TERMINATION HEAD, 10’’ PRODUCTION & 6’’ GAS INJECTION

Decom Engineering was the sole cutting contractor for this scope, for both topside and subsea operations. This involved the cutting of 84mm R4 studless mooring chains, umbilicals and termination heads. 100+ cuts were completed ahead of schedule, resulting in saved vessel time.

PROJECT OVERVIEW

Material: 508mm OD x 40mm WT, X70 steel. Duplex 152mm / 254mm, OD x 38mm WT inner, HD Polyurethane filler.

Water Depth: 900 – 1,000m

Deployment Method: ROV work pack, via hot stabs

Average Cut Time: Termination head: 30 mins; 84mm Mooring Chain: 3 mins; Umbilical: 2 minutes

Blade: 3 – 5 cuts per blade

SOLUTION PROVIDED

Full Equipment and Service Solution

Additional Services: Project management; in-house technicians; logistics management

Additional Equipment and Handling: Hot stabs; buoyancy and other equipment from trusted partners  – supplied on cross-hire

Termination Head, 10’’ Production & 6’’ Gas Injection

EXCEEDING EXPECTATIONS

You’re in safe hands

Working to internationally recognised standards, Decom Engineering raises the benchmark within the pipe cutting industry.